Consider the EZWallet project in FUTURE version (as proposed by the team), assume that you are going to develop the project INDEPENDENT of the deadlines of the course
Estimate by size
Estimate
NC = Estimated number of classes to be developed
7
A = Estimated average size per class, in LOC
300
S = Estimated size of project, in LOC (= NC * A)
2100
E = Estimated effort, in person hours (here use productivity 10 LOC per person hour)
210
C = Estimated cost, in euro (here use 1 person hour cost = 30 euro)
6300
Estimated calendar time, in calendar weeks (Assume team of 4 people, 8 hours per day, 5 days per week )
1.2
Estimate by product decomposition
component name
Estimated effort (person hours)
requirement document
30
GUI prototype
20
design document
25
code
90
unit tests
90
api tests
60
management documents
40
Estimate by activity decomposition
Activity name
Estimated effort (person hours)
requirements plan
45
requirements validation
12
architecture definition
25
module design
30
interface design
15
documentation
30
developmentd enviroment configuration
20
coding modules
70
test plan
10
unit test
80
system test
45
Gantt chart
ID
Activity name
Duration (Day)
Start Finish
Predecessor
1
requirements plan
2
03/04 04/04
2
requirements validation
1
04/04 04/04
1
3
architecture definition
2
05/04 06/4
2
4
module design
2
05/04 06/04
2
5
interface design
2
05/04 06/04
2
6
documentation
2
07/03 10/04
3, 4, 5
7
developmentd enviroment configuration
2
07/04 10/04
3, 4, 5
8
coding modules
3
10/04 12/04
6, 7
9
test plan
1
03/04 03/04
10
unit test
4
04/04 07/04
9
11
system test
2
13/04 13/04
8, 10
Summary
Estimated effort
Estimated duration
estimate by size
210
1.2
estimate by product decomposition
355
1.6
estimate by activity decomposition
382
1.7
As for v1, estimate based on code size is shorter because it doesn't take into account all aspect of activities necessary to complete the project. The others esimates take into account more factor such as planning, design, documentation, ecc, resulting in an higher effort estimate.