Week of 6/3 progress #142

Open
cjmsmith opened this issue Jun 6, 2019 · 0 comments
Open

Week of 6/3 progress #142

cjmsmith opened this issue Jun 6, 2019 · 0 comments

Comments

@cjmsmith
Copy link
Contributor

cjmsmith commented Jun 6, 2019

  • Kanha finished CAD model of the UASB. We will be working to parameterize the model soon.
  • Several materials needed for construction were placed early in the week and came in on Thursday.
    -We will be working on fabrication/welding practice the next few days on the 10" PVC pipe we ordered. Clear PVC pipe (the kind we are actually using to construct the tank of the reactor) are much more expensive, so we want to make sure we know what we're doing before cutting into that.
    --- Practicing drilling holes to insert various pipes, simulating where it will go in the reactor.
  • Currently working on the construction of the tipping bucket; we have cut some pieces to contruct a makeshift frame to hold the tipping bucket. but have not assembled it or attached it to the bucket itself.
  • Abstract submitted for UASB for the 2019 NEGSWS Conference in the fall.
  • Continuing practice on Onshape for some members of UASB.